The Draft Amendments envisage various amendments to the Mineral and Petroleum Resources
Development Regulations (MPRDA Regulations) published in terms of the Mineral and
Petroleum Resources Development Act, No 28 of 2002 (MPRDA) – the most notable of
which are discussed below.

**Consultation Obligations**

The definition of _“interested and affected persons_” has been expanded to refer
specifically to host communities, landowners (both traditional and title deed owners),
traditional authorities, land claimants, lawful land occupiers, holders of informal
rights, the Department of Agriculture, Land Reform and Rural Development, any person(
including on adjacent and non-adjacent properties) whose socio-economic conditions
may be directly affected by the proposed prospecting or mining operation, the Local
Municipality and the relevant Government Departments, agencies and institutions 
responsible for the various aspects of the environment and for infrastructure which
may be affected by the proposed project. Previously, this definition only related
to natural or juristic persons or an association of persons with a direct interest
in the proposed or existing operations or who may be affected by the proposed or
existing operation.

A definition of “_meaningful consultation_” has been included in the Draft Amendments.
The definition contemplates an applicant, in good faith, engaging with the landowner,
lawful occupier and interested and affected parties in respect of the land subject
to the application about the impact the prospecting or mining activities would have
to his right of use of the land by availing all the information pertaining to the
proposed activities enabling these parties to make an informed decision regarding
the impact of the proposed activities. However, we note that the definition of “
meaningful consultation” has not been used in the Draft Amendments and does not 
appear anywhere in the current Regulations.

New regulations are proposed regarding the obligations of:

 * an applicant for a prospecting right, mining right or mining permit to consult,
   which provides that the consultation with landowners, lawful occupiers and interested
   and affected persons contemplated in sections 16(4)(b), 22(4)(b) and 27(5)(a)
   of the MPRDA, shall be conducted in terms of the public participation process
   prescribed in Chapter 6 of the Environmental Impact Assessment Regulations, 2014(
   EIA Regulations); and

 * a holder of a reconnaissance permission, reconnaissance permit, mining permit,
   prospecting permit, and mining right to give at least 21 days written notice 
   of his/her intention to commence with operations to the landowner or lawful occupier
   of the land, as well as the Regional Manager.

**Social and Labour Plans**

The objectives of social and labour plans (SLP/s) have been expanded to include 
mining right holders contributing towards the socio-economic development of labour
sending areas as well as areas in which they operate. Labour sending areas mean 
areas from which a majority of mineworkers, both historical and current, are or 
have been sourced. On this definition, a mining right holder who historically procured
the majority of its workforce from, say, the Eastern Cape, but no longer does so,
would be obliged to contribute to the socio-economic development of that area even
though there are no longer ties to that area.

If a Regional Manager refers a SLP back to an applicant with proposals for amendments,
the revised SLP must then be re-lodged within a period specified by the Regional
Manager, which period may not exceed 30 days.

An applicant for a mining right must also, within 180 days from receiving notification
of the acceptance of the application from the Department of Mineral Resources and
Energy (DMR), consult with communities and the relevant structures of the local,
district and metropolitan municipalities as defined by the Local Government: Municipal
Structure Act, No 117 of 1998 (defined in the Draft Amendments as “Relevant Structures”)
on the content of the SLP to ensure that it addresses the relevant needs of such
communities and is aligned with the updated integrated development plans of such
Relevant Structures. Such consultation process regarding the contents of the SLPs
should also take place in accordance with the public participation process prescribed
in the EIA Regulations.

The Draft Amendments clarify that SLPs need to be approved. We note that neither
the MPRDA nor the current MPRDA Regulations are explicit regarding the requirement
of the approval of SLPs or the process to be followed in relation thereto. Section
23(1)(e) of the MPRDA does, however, provide that the Minister must grant a mining
right if, _inter alia_, the applicant has provided for the prescribed SLP. The Draft
Amendments are specific in that they provide that SLPs which have been approved 
will remain valid until a closure certificate has been issued.

The Draft Amendments also clarify that amendments to approved SLPs will require 
the consent of the Minister in terms of section 102 of the MPRDA. Although section
102 of the MPRDA does not specifically provide for the amendment of a SLP, a SLP
is attached to an approved mining right as an annexure, and forms part of the terms
and conditions of such right through the definition of “_Mining Right_” in the right
itself and is likely thereby covered by section 102 of the MPRDA.

New regulations are proposed regarding:

 * the obligation of mining right holders to publish approved and consulted SLPs
   within 30 days of receiving approval thereof. The publications must be in English
   and one other dominant official language commonly used within the mine community,
   and must be published using the avenues set out in the Draft Amendments. The 
   requirement to publish the approved SLP in “_local newspapers_” appears to be
   an error. SLPs are simply far too voluminous to publish in this manner;

 * the review of a SLP every five years, the first of which will be five years after
   the date on which the SLP was approved. The review process may begin from the
   fourth year in which a SLP has been valid, and during this process affected mine
   communities, adjacent communities, labour sending area, as well as local or district
   municipalities must also be consulted. When reviewing a SLP, the Minister must
   take a number of factors into account, including past compliance with the approved
   SLP, an assessment of annual compliance reports, input and comments from affected
   communities and Relevant Structures, as well as the changing nature of the relevant
   needs of the affected communities as per the integrated development plans of 
   the Relevant Structures;

 * the need to consult with all stakeholders in a transparent and inclusive manner
   when making amendments to approved SLPs; and

 * collaboration on any approved SLP projects taking place in a transparent and 
   inclusive manner and based on consultation with all stakeholders.

**Repeal of Environmental Regulations**

The Draft Amendments also propose repealing all regulations in the MPRDA Regulations
relating to environmental matters, save for regulations 56 (Principles of mine closure),
57 (Application for mine closure), 61 (Closure objectives), and 62 (Contents of 
closure plan).

**New Regulations Relating to section 52 of the MPRDA**

New regulations have been proposed in relation to the notices to be sent to the 
Minister in terms of section 52(1) of the MPRDA. Under the MPRDA, such notices must
be sent by mining right holders where (a) prevailing economic conditions cause the
profit to revenue ratio of a mine to be less than 6% on average for a continuous
period of 12 months, or (b) if any mining operation is to be scaled down or to cease
with the possible effect that 10% or more of the workforce or more than 500 employees,
whichever is the lesser, are likely to be retrenched in any 12 month period.

In terms of the Draft Amendments, a mining right holder must submit a notice pursuant
to section 52(1) of the MPRDA to the Ministe_r “within seven days from the date 
after consultations with registered trade union/s, affected employees or their nominated
beneficiaries, are concluded”_ (own emphasis added). Furthermore, the Draft Amendments
require that mining right holders must submit records of the consultations which
have taken place in terms of section 189 of the Labour Relations Act, No 66 of 1995(
LRA) as well as the status of such consultations as supporting documents to the 
notice. In our opinion, these proposed regulations do not align with how section
52 of the MPRDA has been interpreted up to this point and will be highly problematic
from a practical perspective. By requiring right holders to only send the section
52 notice to the Minister (and thus initiate negotiations with the DMR) after consultations
with trade unions and affected employees have been concluded in terms of section
189 of the LRA, seems to be irrational and may result in additional time delays 
and costs.

The Draft Amendments also provide that a notice sent to the Minister in terms of
section 52(1) of the MPRDA must also be accompanied by, inter alia, a competent 
persons report and a due diligence report as supporting documents. In our opinion,
the requirement to prepare and submit the said reports (whatever they are meant 
to entail) as part of this process is unreasonable and will be troublesome, particularly
where mining right holders are not listed companies. The need for such reports is
not material within this context, and the additional costs and time required to 
prepare the said reports may create unintended consequences and potentially further
job losses.

In addition to the above, the template form for section 52(1) notices provided in
the Draft Amendments contains a provision which states _“the company acknowledges
that the Minister may invoke the provisions of sections 52(3)(c), 93, 47, 99 and
related provisions of the MPRDA to ensure compliance with its requirements.”_ We
note that the inclusion of this provision is highly irregular. Companies should 
not have to agree or acknowledge the application of the mentioned sections as part
of this process. The applicability of the mentioned sections of the MPRDA should
only be determined as a matter of law.

**New Regulations relating to Applications for the Use of the Surface of Land Contrary
to the Objects of the MPRDA**

In terms of section 53 of the MPRDA, any person who intends to use the surface of
any land in a manner which may be contrary to the objects of the MPRDA or is likely
to impede such objects, must apply to the Minister for approval in the prescribed
manner.

New regulations have been proposed in the Draft Amendments which set out the specific
information that applicants will need to provide as part of a section 53 application.
Until now, there has been no prescribed format for a section 53 application. However,
the DMR published a template for such applications, which is aligned with what is
now set out in the Draft Amendments. The difficulty which applicants under section
53 face in practice is that certain information required under these regulations
is not readily available. For example, applicants will be required to confirm, inter
alia, whether holders of prospecting, mining, exploration or production rights within
a two-kilometre radius of the application area have been identified, and if so, 
whether they have been consulted and/or objected to the proposed land development.
In our experience, applicants are only made aware of whether any parties hold mineral
rights in relation to the application area (and possibly the surrounding area) once
the section 53 application is processed by the DMR, and the applicants have been
directed by the DMR to consult with any such parties who hold or have applied for
rights under the MPRDA. Applications for information under the Promotion of Access
to Information Act, No 2 of 2000 can be lengthy processes and are not therefore 
particularly helpful.

**New Regulations Relating to Section 54 of the MPRDA**

In terms of section 54 of the MPRDA, a right holder should notify the relevant Regional
Manager where a landowner or the lawful occupier of the land prevents the holder
from commencing or conducting any reconnaissance, prospecting or mining operations
by (a) refusing entrance to the land; (b) placing unreasonable demands in return
for access to the land; or (c) if the landowner cannot be found in order to apply
for access to the land. The Regional Manager is obliged to follow certain processes
as set out in section 54, and in terms of section 54(4) of the MPRDA, in the event
that parties then fail to reach agreement on the amount of compensation payable 
due to the loss or damage suffered, the parties are entitled to refer the matter
either to arbitration or a competent court for determination.

New regulations have been proposed in the Draft Amendments regarding how disputes
envisaged in section 54 of the MPRDA will be resolved and the process set out therein
is inconsistent with what is set out in section 54.

In terms of the Draft Amendments, once notice has been sent to a Regional Manager
in terms of section 54 of the MPRDA and provided the dispute cannot be resolved 
by the Regional Manager, the parties will be required to refer the matter to either
an arbitration or conciliation process. Only in circumstances where the arbitration
or conciliation process fails, will an aggrieved party be entitled to refer the 
dispute to a competent court for determination.

Furthermore, a non-refundable fee of R1,500 per notice will be payable by the right
holder, which is not contemplated in the MPRDA. It is unclear whether a landowner
who submits a notice in terms of section 54(7) will also be liable for the payment
of such fee. Frequently, it is impoverished communities who file such notices, and
the additional fee would be burdensome.

**Appeals**

Under the Draft Amendments, substantial amendments to the MPRDA Regulations relating
to appeals against administrative decisions have been proposed. A number of the 
proposed amendments seem to be problematic and may create uncertainty in practice
if accepted. It should be noted that the reference in section 74(10)(b) of the Draft
Amendments to “answering affidavit” is clearly wrong and should be read as “answering
statement”.

Within this context, it is important to highlight the distinction between appeals
against administrative decisions submitted in terms of sections 96(1)(a) and 96(
1)(b) of the MPRDA. An appeal in terms of section 96(1)(a) of the MPRDA will be 
submitted to the Director-General where a party wishes to appeal an administrative
decision made by a Regional Manager (or a designated person to whom power has been
delegated or authority has been assigned). An appeal in terms of section 96(1)(b)
of the MPRDA will be submitted to the Minister where a party wishes to appeal an
administrative decision made by a Director-General (or the designated agency). The
Draft Amendments do not appear to recognise the distinction between appeals submitted
under these two sub-sections and seem to only apply to appeals submitted pursuant
to section 96(1)(a) of the MPRDA. The manner in which appeals submitted in terms
of section 96(1)(b) of the MPRDA will be processed and the time periods applicable
thereto appears to have been left open, which will create uncertainty going forward.
Furthermore, the proposed amendments appear to remove the responsibility of the 
Director-General to adjudicate appeals submitted pursuant to section 96(1)(a) of
the MPRDA and place this obligation on the Minister instead. It appears as though
the intention behind the Draft Amendments in this regard is to make the Minister
the sole authority responsible for adjudicating appeals against administrative decisions.
In practice, although the Draft Amendments do set out specific time periods within
which each step of the appeal process must take place, the ability of the Minister
to take on the additional work contemplated by this proposed amendment and whether
this will result in timing delays has to be questioned.

A further issue created by the Draft Amendments relates to the time period within
which a party may submit a written notice of its intention to appeal an administrative
decision. Currently, under the MPRDA Regulations, any person who intends to appeal
an administrative decision in terms of section 96 of the MPRDA must submit written
notice of its intention to appeal to the Director-General or the Minister (as the
case may be) within 30 days of becoming aware of the administrative decision. In
terms of the Draft Amendments, the notice of intention to appeal a decision in terms
of section 96(1)(a) of the MPRDA has to be submitted in writing within 30 days of
the administrative decision being made. This proposed amendment has the potential
to be problematic, as in practice, it is common for parties to whom these provisions
may apply to only become aware that an administrative decision has been made later
than 30 days after the date of the decision. The consequence of the proposed amendments
will therefore be that persons who had a right to appeal an administrative decision
being potentially prevented from doing so, due to no fault of their own.

In terms of regulation 15 of the Draft Amendments, in circumstances where the Minister
receives an appeal which covers matters to be adjudicated on in terms of both sections
96(1)(a) and 96(1)(b) of the MPRDA, a copy of the appeal must be submitted to the
Minister of Environmental Affairs _“for processing in relation to environmental 
matters in accordance with the procedure set out in section 96(1)(b)”, and the Minister(
of Mineral Resources and Energy) and the Minister of Environmental Affairs “shall
co-ordinate the finalisation of simultaneous appeals in terms of section 96(1)(a)
and (b) of the MPRDA respectively affecting the same administrative decision.”_ 
We note that this proposed regulation is unclear and appears to be incorrect for
a number of reasons. Firstly, as mentioned previously, there is a distinction between
the types of appeals submitted under sections 96(1)(a) and (b) of the MPRDA – and
as such, there should never be a scenario where as part of one appeal, an administrative
decision of a Regional Manager as well as an administrative decision of a Director-
General are submitted together at the same time. Secondly, based on the manner in
which this proposed regulation is drafted, copies of all appeals submitted in terms
of section 96(1) of the MPRDA will also have to be submitted to the Minister of 
Environmental Affairs, regardless of whether an appeal relates to an environmental
matter or not. We recommend that this proposed regulation be amended to provide 
certainty in relation to the instances when the Minister of Environmental Affairs
must be involved in adjudicating appeals submitted in terms of section 96(1) of 
the MPRDA.